#WBS CHART PRO PROJECT 2013 CODE#
But unlike outline numbers, the levels of the code can be represented as uppercase or lowercase letters, numbers, or characters (a combination of uppercase and lowercase letters and numbers), depending on which you specify for each level in the code mask when you create the WBS code. Each level of the WBS code represents an outline level in the task list. You can define one set of custom WBS codes per project and display it in the WBS field.

The second type of WBS code is a custom code that you define. Outline numbers consist of numbers only, and you can’t edit them, but they change automatically when you move a task up or down in the task list or indent or outdent tasks. Outline numbers are the simplest type of WBS code Microsoft Project calculates outline numbers for each task based on the outline structure of the task list. There are two types of WBS codes in Microsoft Project. WBS codes can be used for reporting schedules and tracking costs. Work breakdown structure (WBS) codes are alphanumeric codes that identify each task’s unique place in the outline structure of your project. Microsoft Project Work Breakdown Structure codes, if using the Outline Number sequence, can also be displayed in within the Task Name cells. You can see how the automatic WBS code is based on the task IDs. This is done simply by inserting a column and adding a custom name. To make working with WBS codes easy, you can add a column to a sheet view.

Microsoft Project Work Breakdown Structure codes use a multilevel bullet point number sequence from the Outline Number field by default, although this can be customised. A WBS code identifies a task’s unique place in the structure of your project.

With Microsoft Project, you can represent the work breakdown structure by using task IDs or by assigning your own WBS code to each task. WBS Codes and Viewing a WBS Working with a Work Breakdown Structure (WBS)Ī WBS is a hierarchical structure used to organise tasks for reporting schedules and tracking costs. Each descending level represents an increasingly detailed description of a project component. As a deliverable-oriented grouping of project elements, a WBS chart organizes and defines the total scope of the project. Useful for a quick, high-level view of the parts of your project, a WBS is often shown as a block diagram. They also help you identify logical groupings of tasks and establish the focus of the project to prevent unintended future changes. WBS descriptions define how the result will be accomplished. What is a work breakdown structure?Ī WBS is a top-down planning method that defines the desired end result of a project and is made up of related elements, often called work packages, work elements, work phases, or tasks (summary tasks and subtasks). Microsoft Project Work Breakdown Structure defaults to the Outline Number sequence you would expect to see in a multi-level bullet point list. It can also help establish clear project goals. Many organizations apply a WBS numbering standard to define projects, because it’s an important planning tool that serves as a basis for project scheduling, reporting, staffing, and budgeting. All Rights Reserved.In project management, a Work Breakdown Structure (WBS) is a method for analysing a project’s activities.